Canberra light rail – Stage 1

PROJECT DESCRIPTION

Light rail system serving the city of Canberra

Canberra’s light rail was designed to form part of the city’s growing integrated transport system, which aims to connect people with employment, social and cultural hubs, reduce congestion, and ensure Canberra continues to be one of Australia’s most livable cities.

Stage One of the project has been delivered under a Public Private Partnership between the ACT Government and the Canberra Metro consortium, which consists of CIMIC Group companies, Pacific Partnerships, CPB Contractors and UGL, with partners John Holland

This first phase of the city-wide light rail network is a twelve-kilometre route that connects the northern area of Gungahlin to Canberra’s City centre.

This stage commenced with first sod turning on 12/07/2016 & finilaised with first public servicing on 20/04/2019

The light rail has been designed to run every six minutes during peak times with 13 stops on the 12km journey, travelling from the City to Gungahlin along Northbourne Avenue, the Federal Highway, and Flemington Road.

Stats and Facts

During the delivery of Stage 1 of light rail from Gungahlin to the City:

  • 14 Light Rail vehicles
  • 13 stops
  • 12km total distance
  • 442 cctv cameras
  • 276 passenger information display boards
  • 166 help points
  • 1494 trips per week
  • 18000 km travelled per week
  • 5,000 People worked on the project – 300+ Local businesses have been involved in the project – 70% Project workforce from Canberra and surrounds – 26KM Total rail track laid for Stage 1 – 382 Overhead wire poles stood – 1,200+ Trees planted along Light Rail corridor

Abyss Construction completed:

  • FRP track slabs.
  • Retaining walls.
  • Creek crossings/bridges.
  • Traffic & street light footings
  • Labour hire
  • Plant hire

 

Request a Quote

Name(Required)

Project information

Abyss Construction completed – FRF installation to green track prototype stage 2A

Head Contractor:

Canberra Metro

Date:

6/10/2017 First rail laid – 28/10/2018 final rail laid

23/10/2017 Abyss started

20/04/2019 Service start operating

Project value:

$675m

Package value:

$3.95m

Location:

Key People For This Project:

Cathal O’Braonain

Sector

Road and rail
Government