PROJECT : Burrill Lake Bridge

CLIENT : Road and Marine Services (RMS)

CONTRACTOR : BGC Contracting

LOCATION : Ulladulla

SECTOR :  Infrastructure – Road

PROJECT VALUE : $58 million

PACKAGE VALUE : $ 2.3 million

Project Description :

The new bridge and highway would be higher than the future 1 in 100 year flood level and reduce the impact of flooding. Complete removal of the existing causeway and bridge, 5000 tonnes of concrete used, 500 tonnes of steel used, 6000 meters of utility services installed.

Our Scope Included :

  • Install bridge planks.
  • Install formwork tie steel, install cast ins and pour concrete to deck slabs.
  • Install parapets (with Abyss costum Installation jig) and stich pour to deck slab.
  • Install formwork, steel reinforcement, castin items and pour concrete to crash barriers.
  • Install guard rails on top of crash barriers and parpets.
  • Install suspended undermount bridge drainage system.
  • Install cast insitue drainage junction and pump pits.
  • Install formwork, steel reinforcement and pour concrete to roundabouts and foothpaths.